Summary
The Board approved payments for permanent and temporary easements for the Broughton Road bridge project, agreeing to pay Gail Hauserman $350 for a small parcel and using a formula of $5,645.16 per acre to compensate the other two landowners; the motion passed unanimously.
Get email alerts on the Right Of Way topic
No spam. Unsubscribe anytime.
Gail Hauserman and Brady Hedstrom of BG Consultants met with the Clay County Board to discuss right‑of‑way acquisition for the upcoming Broughton Road bridge project. The planned acquisition includes both permanent and temporary easements; temporary easements will revert after 12 months.
Commissioner Mayo offered $350 to Ms. Hauserman for a small section of ground. Commissioner Carlson moved to pay Ms. Hauserman $350 and to compensate the remaining two landowners at the formula rate of $5,645.16 per acre. Commissioner Mayo seconded; the motion passed unanimously. The minutes record the payment formula and unanimous approval but do not list parcel acreage or the names of the other two landowners.