Road and Bridge reports completed bridge work, fiber line damage and rock budget balance
Summary
Road and Bridge Superintendent Joe Gardner told the commissioners about bridge progress on J4/246 and W4, a fiber line cut during excavation being handled through insurance, ongoing chip-and-seal work, delivery of 500 tons of rock, energy fees totaling $4,730.72, and a rock budget balance of $424,748.91.
Get email alerts on the Road And Bridge Operations topic
No spam. Unsubscribe anytime.
Road and Bridge Superintendent Joe Gardner updated the Board on multiple operational items, including bridge work, an excavation-related fiber cut, safety issues from a KDOL inspection, and the county's rock inventory and budget.
Gardner reported the J4 and 246 Roads bridge replacement completed last year has been assigned a new number and the north side of the W4 bridge is now completed. Crews discovered exposed insulation at a charging area during a recent Kansas Department of Labor inspection and had questions from the inspector about an eye wash station that is tied to well water. Gardner also reported that county crews unintentionally struck a fiber line while digging in a marked area; the invoice from Rainbow has been turned into insurance after crews were given the go-ahead to excavate. He said crews began receiving 500 tons of rock from the Soldier quarry and reported energy fees billed through May 22 totaling $4,730.72 and a rock budget balance of $424,748.91.
The Board noted resident concerns about dust on the road to the J6 feedlot and was told the feedlot missed the county dust-control purchase deadline and planned to hire a private contractor. Road and Bridge also reported in-house servicing of a truck and scheduling of other vehicle maintenance.