Troup County staff recommends adding third apparatus bay to Station 14; cost estimated at $329,000

Troup County Board of Commissioners · January 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff asked commissioners to approve adding a third apparatus bay to the new Station 14 during initial construction, saying it would be easier and cheaper to include now; staff reported a negotiated price of $329,000 and identified additional value-engineering savings and a 5% contingency in the project budget.

County staff told commissioners on Jan. 6 that it would be fiscally and operationally prudent to add a third apparatus bay to the new Station 14 at 3157 Roanoke Road while the contractor is still on site.

"We were able to cut $41,000 out of [the price for the third bay] and get the price for that apparatus bay down to $329,000," Jay Anderson said, describing value-engineering discussions with Principal Construction. Anderson told the board that the base bid originally approved was for a two-bay station with living quarters and site work; adding a third bay now would minimize later disruption and provide long-term flexibility for special-operations equipment.

Director of public safety Zach Steele and other staff said the third bay would primarily be used for special-operations equipment — boats, dive trailers and other marine or rural-response apparatus — and that staff anticipate working through deployment analysis and staffing adjustments over 30–180 day intervals after the station opens. Anderson reported about $45,000 of additional savings identified on the base bid and noted a 5% contingency line (approximately $150,000) remained in the project budget.

Staff asked the board for direction on whether to include the third bay as part of the current construction contract; Anderson said the item will be presented to the full board for consideration at the evening meeting and that funding options (including the previously discussed 50/50 split between sources) would be identified there.