County approves testing and concrete cutting for Circular Butte shop expansion
Summary
Jefferson County approved a Civil Science proposal to core and test the foundation and map rebar for the Circular Butte shop expansion at an estimated $2,515, and approved EC Concrete Cutting for $775 for concrete cutting required by the building permit.
Get email alerts on the Public Works Foundation Testing topic
No spam. Unsubscribe anytime.
Sam Scott, county engineer, told the board the old shop expansion requires a structural engineer’s approval for the building permit. He presented a Civil Science bid to core and test concrete and to map rebar in footings and foundation to certify the structure.
Commissioner Young moved to approve Civil Science to test and certify the foundation at the old shop at an estimated cost of $2,515; Commissioner Clark seconded and the motion passed on roll call. The board also approved concrete cutting by EC Concrete Cutting for $775 under a separate motion that passed unanimously.
The approvals respond to permit requirements; the engineer indicated those tests and mapping are necessary before the county can proceed with the expansion. No additional funding source was specified in the meeting record.