County approves $437,238 contract for Gage Park Playland surfacing; opening targeted for late August

Shawnee County Board of County Commissioners · July 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved contract C2026277 with TaylorMade Co. to install approximately 25,399 square feet of safety surfacing at Gage Park Playland using Gage Park sales tax funds. Parks staff said they expect the play area to be ready by the Labor Day weekend.

The Shawnee County Parks and Recreation Department received commission approval to move forward with surfacing at the Gage Park Playland.

Parks Director Tim Lorett asked the board to approve contract C2026277 with TaylorMade Co., funded by Gage Park sales-tax funds, at a cost of $437,238.61 for roughly 25,399 square feet of safety surfacing. "This is 25,399 square feet of safety surfacing," Lorett said, describing a mix of poured-in-place surfacing, artificial turf and bonded rubber and noting work on the aggregate subbase and drainage.

Lorett said, if the schedule holds, staff expect to open the Playland by the Labor Day weekend. Commissioners approved the contract on motion and second.