Director Warren reports progress and timeline for FY26 paving program
Summary
Director Warren reported the FY26 paving map is mostly complete; remaining streets (marked brown and purple) require cleanup and striping, with contractor work and striping expected to finish by week’s end.
Get email alerts on the Public Works Paving topic
No spam. Unsubscribe anytime.
Director Warren gave the board a map-based update on the FY26 paving program, saying that all roads shown on the map except those marked in brown and purple have been completed. He said the pavement contractor will return to finish cleanup of excess gravel and crews are trying to schedule striping to complete the work by the end of the week.
Warren described the cleanup as part of normal milling and paving operations: "It's some of the excess gravel that we've been dealing with... They're gonna be back to continue to clean up." The update identified a small number of remaining maintenance items and set expectations for finishing striping and cleanup within days.