Council approves Change Order #5 that adds $21,770 manual transfer switch to water project
Summary
Council approved Change Order #5 for the Milbank Water Supply Improvement project, yielding a net increase of $10,306 and adding 10 days to the schedule; the order includes a $21,770 addition for a manual transfer switch and other line‑item deductions.
Get email alerts on the Water Supply Project topic
No spam. Unsubscribe anytime.
The Milbank City Council approved Change Order #5 to the Milbank Water Supply Improvement project on March 10, producing a net contract increase of $10,306 and extending the substantial completion date by ten days.
According to the project note presented at the meeting, the order includes a $3,505 deduction for reuse of an existing service conduit and a $7,959.10 deduction for the ATS move at the pump house, offset by a $21,770 charge for "the addition of a manual transfer switch used between well house one and three." Councilmember Josh Karels moved for approval and Mike Hanson seconded; the motion passed 5‑0.