Board approves CMAR amendment and $6.44 million GMP for Public Works facility
Summary
Commissioners authorized Amendment 1 to use a Construction Manager at Risk and approved a guaranteed maximum price (GMP) of $6,437,415 with a substantial completion date of Aug. 15, 2025, after staff outlined scope deducts and contingencies.
Get email alerts on the Public Works Construction topic
No spam. Unsubscribe anytime.
The commission approved Amendment 1 to the Public Works combined facility contract, moving the project to a Construction Manager at Risk (CMAR) delivery and establishing a guaranteed maximum price (GMP) of $6,437,415.
Public Works Director Gene Legurski explained that initial hard bids had been significantly over budget, prompting a CMAR approach with Groat House Construction. Legurski identified three deducts that preserved core building integrity while cutting costs; with those adjustments the GMP came in about $14,983 over the previously budgeted $6,422,432, but included a $277,195 contingency for owner-directed changes. "If we run this project correctly... we can save a ton of that money," Legurski told the board.
Commissioners discussed the project timeline (substantial completion estimated 08/15/2025) and the fiscal-year cashflow: roughly 80'85% of the project cost is expected in the current fiscal year. The board voted to approve the amendment and GMP; staff will proceed with a pre-bid for subcontractors and return with budget details for next-year planning.