Wastewater staff report E. coli exceedances post‑UV; targeted cleaning and pipe work planned
Summary
Operations staff reported E. coli exceedances after the UV stage and presented a corrective plan (system emptying, chlorination/dechlorination and cleaning); staff also flagged root intrusion in the line to the river and said targeted pipe replacement or jetting will be needed to avoid permit violations.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
The wastewater operator reported January flows and flagged that some post‑UV samples exceeded permit E. coli limits. Staff outlined an immediate remedial plan: temporarily stopping flow, emptying and bleaching the affected chamber, dechlorinating and returning flows after cleaning, and targeting parts of the conveyance line that show root intrusion for repair or localized replacement.
Operations staff emphasized the importance of addressing the line before a large flow event; they said a full replacement farther into the river is a larger, more expensive option but that removing and replacing a few damaged sections could be done with a much smaller budget. Staff promised to return with bids or proposals and to coordinate scheduling to avoid permit non‑compliance.