Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities topic

No spam. Unsubscribe anytime.

City administrator reports City Hall hardening progress and upcoming Public Safety Building estimates

City of Okeechobee City Council · May 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Administrator reported windows ordered for the City Hall hardening project (one additional window added), roof repairs completed, roof tiles delivered, and Proctor Construction preparing exterior renovation estimates for the Public Safety Building; a mural quote of $3,000–$4,000 was noted.

City Administrator provided a status update on the City Hall Hardening Project: windows have been ordered, with one additional window identified and ordered; roof leaks have been repaired; roof tiles have been delivered; and Proctor Construction will perform reroofing once exterior painting is complete. The administrator said staff received a quote of $3,000–$4,000 to replace the City Seal mural and will collect additional quotes before presenting costs to the council.

Proctor Construction is completing the estimating process for exterior renovations to the Public Safety Building and staff intends to present a design-build contract and mural quotes to the council at a later meeting. The update was informational and did not include a formal vote.