Provallis site work complete; elevator and HVAC delays push interior fit‑out timeline toward October
Summary
Town staff said the Provallis (Project TPOT) site has utility and stormwater upgrades complete and servers staged, but elevator vendor availability and HVAC issues are delaying full occupancy; staff expects the building to be ready for equipment load‑in in mid‑late August and to be operational by October 1 if remaining issues are resolved.
Get email alerts on the Development Project Updates topic
No spam. Unsubscribe anytime.
Staff gave a status update on the Provallis build‑out (referred to in the meeting as Project TPOT), reporting that utility telecom and stormwater upgrades are complete and that crews have buried utilities in preparation for vertical construction.
A town project representative explained that the current critical path items are the elevator and some HVAC work. "Our big lead item is gonna be the elevator," the representative said, and noted there are a limited number of elevator vendors, which can create schedule risk. Staff said servers are already set up in the space and the plan calls for equipment load‑in once the elevator and final HVAC tasks are finished.
Staff projected a surface‑level completion milestone in mid to late August and a target date for the building to be ready for operations on October 1, subject to successful completion of elevator and HVAC work. The council and staff discussed how the project’s timetable affects security, IT infrastructure, and noncompliance windows related to the move‑in schedule.
Council members asked for caution about setting hard dates given vendor lead times, and staff recommended continuing coordination with contractors and vendors to meet the October target where possible.