Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Supervisors approve water and electric hookups for new county cold‑storage

Chickasaw County Board of Supervisors · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chickasaw County supervisors approved contracts to install water and electrical service at the new county conservation cold‑storage building, accepting quotes of $8,440 for water and $9,007.35 for electrical work to be paid from the county betterment fund.

Chair (S1) told the board the builders had poured concrete and the walls were expected to go up within days and presented two vendor quotes to bring utilities to the New County Conservation Cold Storage building. The chair said the water hookup quote is $8,440 and that Scanlon Electric submitted a quote for electrical work of $9,007.35, both under the county's $10,000 bid threshold and payable from the county betterment fund.

"We get all that copy of those $9,007.35," the chair said while explaining the project budget. Board members moved to award the electrical contract and the water hookup: motion by Travis, second by Steve to allow Standard Electric at $9,007.35 and to authorize the companion water work. The motion carried on a voice vote with no recorded opposition.

The chair noted those expenditures fit within the $200,000 budgeted for the Twin Pounds Cold Storage Building and said about $44,000 would remain from that line after paying dirt, building, water and electric costs. The board did not specify an exact construction completion date beyond the chair's comment that the building work should be finished "by Friday."