Parvin Park construction underway; concrete placement nearly complete
Summary
Parvin Park construction began March 31 and is expected to run into early fall; concrete placement is 90% complete, playground drainage and limestone edging are in progress, and the project's gazebo pour and building permit were reported finished and approved.
Get email alerts on the Parks Construction topic
No spam. Unsubscribe anytime.
Staff provided a detailed update on Parvin Park, a smaller downtown park whose scope includes a loop trail, playground, gazebo, picnic tables, a drinking fountain and parking. Construction began March 31 and is expected to continue into early fall; staff said concrete placement for the project is roughly 90% complete.
The presenter said contractors have formed the playground edge, installed gravel under the drainage system, and placed large limestone blocks around the playground perimeter. A small grain-bin–style gazebo pour is complete and the permitting department has approved the building permit. No schedule changes or funding requests were made in the public comments.