Raymond Community Park reported 94% complete; well and pump remain

Prosper Parks and Recreation Board ยท June 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said site work at Raymond Community Park is 94% complete, the playground is finished, and project completion awaits a contractor finishing a well and pump; the architect approved the building during a recent final walkthrough.

A parks presenter reported that Raymond Community Park site installation is about 94% complete and that the only significant remaining work is contractor completion of a well and pump at the far end of the site. The playground is complete, and staff said they completed a final walkthrough with the landscape architect and architect, who approved the building.

The presenter noted some shrub and plant-bed replacements are required since the park opened in February and that work to tie in a trail with Public Works to First Street is underway. "I don't have any concerns as yet," the presenter said about the project schedule; well and pump construction were described as roughly 85% complete in the presentation.