Council approves two pay certificates totaling $147,427.65 for Hickman Pickleball Park construction

City Council of Hickman, Nebraska · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Certificate #2 for $87,245.15 and Certificate #3 for $60,182.50 to Raughey General Contractors for the Hickman Pickleball Park; staff reported site/utility completion percentages and a target substantial completion timeline.

City staff presented progress and payment requests for the Hickman Pickleball Park. Kelly said site work is about 87% complete, underground utilities 83% complete, irrigation 30% complete, sidewalks and paving 11% complete and the pickleball courts about 5% complete as the contractor installs post-tension posts. The council approved Certificate #2 to Raughey General Contractors for $87,245.15 and Certificate #3 for $60,182.50.

Kelly outlined a schedule that shows electrical finishes, final grade/seed irrigation by late August, final inspections at the end of August and substantial completion around early September, subject to concrete curing times. "They're really getting some stuff done now," Kelly said, noting the underground utility progress from prior pay apps.