WMP update on new schedule; first draft due June 17 after contract delay
Summary
The WMP Subcommittee learned the consultant has begun drafting the Watershed Management Plan and set a revised timeline that pushes the project about one quarter behind the original schedule; the first draft is due June 17, 2026.
Get email alerts on the Wmp Schedule topic
No spam. Unsubscribe anytime.
Martha “Muffy” Carter, chair of the Watershed Management Plan Subcommittee of the Lake Management Advisory Committee, opened a June 3 phone check-in to review progress on the WMP update and confirmed new draft milestones. The consultant, Carl Nielson of Wilcox & Barton, has just started drafting the document, and the subcommittee set a first-draft deadline of June 17, 2026, with member comments due by June 20 and a second draft circulated to LMAC members by June 24.
The revised schedule calls for discussion at the LMAC meeting on July 1, a third draft around July 15, a penultimate draft roughly between Aug. 30 and Sept. 15, and a final document by Sept. 30, 2026. Committee members said the revised timeline places the project about one quarter behind the original plan; Henry Beck was noted as unavailable for the June review window (June 5–28).