Council approves $345,796 waterline change order tied to Highway 80 utility relocations
Summary
Council approved Change Order 15 for the US Highway 80 utility relocation project: $345,796.42 to upsize and replace 655 linear feet of 8‑inch waterline with a new 24‑inch main. Staff noted a $10,707.88 savings in specialized fittings and said work will require nighttime lane closures.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Chris Cox presented Change Order 15 for the Highway 80 utility relocation: unforeseen as‑built differences required upsizing and replacing 655 linear feet of existing 8‑inch waterline with a new 24‑inch waterline. The change order amount is $345,796.42; staff identified a $10,707.88 savings by reducing the number of specialized RCCP fittings from three to two.
Cox said the work is tied to TxDOT-mandated relocations for the Highway 80 reconstruction and that crews will plan for nighttime operations and lane closures for safety and traffic control. Council asked funding questions and Cox said the cost will come from the town's water and sewer fund. Council approved the change order 5–0 and staff said materials can be ordered immediately with work anticipated to begin after delivery (roughly two weeks for procurement, with tie‑in work performed during planned nighttime closures).