Council authorizes change order for Lake Road/Douglas Drive sewer project; contingency covered by DIFA loan

Bay Village City Council · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council reviewed and moved forward with a change order for the Lake Road/Douglas Drive Sewer Improvement Project after unanticipated underground conflicts. The administration said contingency funds of $163,965.70 would be covered under a DIFA loan; the revised contract total was cited as $362,135.63.

Public-works staff told council that unforeseen subsurface conditions on the Lake Road/Douglas Drive Sewer Improvement Project required moving water and sewer mains and raising sidewalks, creating additional labor and material needs that exceed the original contract.

"Out of contingency, we're looking at $163,965.70. And so, we're looking at $163,965.70," the service director reported when detailing the requested change order; staff said the final contract amount would be up to $362,135.63 and that some Cleveland Water costs would be billed back separately. Council discussed the DIFA loan terms (30-year repayment at under 3% interest was described as the administration's working assumption) and asked for follow-up documentation on loan terms and amortization schedules.

Committee members said this was likely the final change order on the project, and staff confirmed that the contract required return visits by the contractor in spring to perform restoration work on tree lawns and landscaping. Council approved the authorization to proceed and to advertise remaining bid items for related projects.