Summary

6 More Architects told Bay Village council the Dwyer Center (likely built c.1940) has extensive envelope, MEP, accessibility and site problems that would require gut renovation. Staff and some council members said a replacement building on the existing site may better meet long-term senior and recreation needs; further site study and rec-commission input were requested.

City-hired consultants from 6 More Architects presented a building assessment of the Dwyer Center, outlining widespread structural and systems deficiencies and limited expansion opportunities at the building's current location.

"The envelope of the building ... is leaking. It is poorly insulated, it leaks like a sieve," the architect said, also listing broken pipes, undersized electrical service that requires temporary generators for events, multiple residential-style furnaces, moisture-damaged parquet floors, and restrooms that interrupt main-hall usage. The consultant advised that renovating the existing structure would require pulling back to the studs and rebuilding many systems and that such work would significantly disrupt operations.

Council and staff discussed options including building a replacement north or west of the current facility so the existing center could remain open during construction. Staff emphasized the need to check subsurface conditions (sewer, foundations) at candidate sites, and the council signaled support to continue the study through the Committee of the Whole and to gather rec commission and community input before selecting a path.

Council members stressed the importance of sizing any new facility to Bay Village's long-term service needs for seniors and recreation, and indicated a likely timeline of further study and architect qualifications work later in the year.