Council approves engineering study for Stafford Civic Center after debate over schedule and costs
Summary
The Stafford City Council approved a proposal from Stanley Spurling & Hamilton Inc. to perform geotechnical and engineering investigations at the Stafford Civic Center, authorizing the mayor to execute the contract. Council members debated timing, potential venue closures for testing and funding shortfalls.
Get email alerts on the Civic Center topic
No spam. Unsubscribe anytime.
The Stafford City Council on June 3 approved a proposal from Stanley Spurling & Hamilton Inc. to perform geotechnical borings, sewer-line video and an engineering assessment of the Stafford Civic Center. Councilmember 4 moved to approve the proposal and authorized the mayor to sign the agreement; the motion passed on a voice vote.
Council members split over timing and budget. A city presenter told the council the study would include interior borings and sewer televising to assess foundation, pipe separations and structural needs. The consultant urged the council to approve the study before deciding whether to invest in repairs or demolition: “I think you can't decide that if you don't do this study,” said the presenter (speaker 11). Councilmember 4 summarized the position for several members: “We need this data, so we can know... what the actual costs are going to be,” and said delaying the study would hamper an informed decision.
Staff and council discussed schedule constraints tied to existing bookings. Staff reported Civic Center revenues of about $157,001.77 in 2024 and $182,009.95 in 2025 and cautioned that many dates are already held through February; consultants estimated the study would take roughly three months from approval, with pockets of work that could be staged around bookings. Councillors pressed for clarity about liability and whether contractors would remediate damage to carpet or finishes; consultants said cores and patches would be performed to keep the facility usable and that damage costs would be handled through contract provisions or insurance where appropriate.
The study cost and funding were a frequent concern: presenters said a roughly $100,000 balance existed in an account but that full funding may require additional budget action. After debate about whether to delay work to February when bookings are lighter or proceed now with staged access, council approved the engineering proposal and directed staff to coordinate schedules and follow-up reporting.