Superintendent details construction progress across Northbrook SD 28 schools
Summary
Superintendent gave a detailed construction and readiness update, reporting Meadowbrook gym at ~95% complete, parking and paving timelines (Meadowbrook south lot expected by Aug. 10), ongoing foundation work at Greenbrier and planned blacktop extensions and utilities work at Westmore.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Superintendent delivered a multi‑school construction update and timeline as the district prepares for the 2026–27 school year, saying crews have accelerated summer work so safe arrival and dismissal procedures are in place when classes begin.
"If you've been by the schools, you know that there's a lot of activity at all of our buildings," the superintendent said, noting the Meadowbrook gym is about "95% complete" and that the Meadowbrook south parking lot paving is "being told... will be complete by the August 10," a date the district flagged as important for parking and traffic flow. He described a partially completed south storm trap that the contractor expects to finish soon and explained the district is coordinating with the village on additional stormwater infrastructure.
The superintendent also walked the board through site progress at Greenbrier and Westmore: building pads at Greenbrier are complete with foundations and utilities underway; Westmore has finished its building pad with slab and framing scheduled soon and an asphalt extension beginning 07/28. He said the district negotiated shared parking with a nearby Methodist Church and with the Park District to reduce neighborhood street parking during construction days.
Board members approved several construction pay applications later in the meeting. The superintendent closed the update by saying crews are "hitting the ground running" and that the district will continue to share aerial photos and schedule updates as projects progress.