Board approves guaranteed maximum prices for three district projects totaling roughly $23.6 million

Cedar Hill Independent School District Board of Trustees · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees unanimously approved GMPs with Core Construction for Waterford Oaks (approx. $12.15M), Plummer renovation (approx. $9.09M) and Lacey Enrollment Phase 2 (approx. $2.4M), with the administration noting value-engineering and an overall under-budget outcome across projects.

The board approved Guaranteed Maximum Prices (GMPs) for three bond-funded construction projects with Core Construction: Waterford Oaks (~$12,152,000), Plummer Elementary renovation (~$9,085,000) and Lacey Enrollment Center Phase 2 (~$2,400,000). Construction presenter Josh Gaines said teams used value engineering to bring most projects under budget and that the combined projects were under budget by roughly $215,000.

Gaines walked trustees through scope adjustments (reducing soil prep and optimizing civil work) and noted safety-and-security additions (PA systems, clocks and cameras) that increased costs at some sites. Trustee discussion requested clearer asterisks on publicly posted documents to show where increases occurred; Gaines acknowledged the request and noted the presentation includes a footnote identifying increases on Waterford Oaks and Lacey items.

A motion to approve the GMPs was moved and seconded; trustees voted unanimously to approve the guaranteed maximum prices to Core Construction for the named projects.