Contractor to mobilize this week on Southwest parking lot; mid-May completion required for summer events
Summary
Staff told the Committee the Southwest parking lot contractor will mobilize this week (start clarified to Wednesday) and must finish by mid-May so the area is available for scheduled summer activities.
Get email alerts on the Parking Infrastructure topic
No spam. Unsubscribe anytime.
The Committee heard an expedited schedule for the Southwest parking lot project. Engineer Glenn Davis said contractors planned to mobilize immediately and staff coordinated with businesses to provide alternate parking and maintain delivery access.
Director Matt Hiscock clarified the contractor would start on Wednesday of the week in question, following weather delays. Davis said the contractor has a firm mid-May completion date to ensure the site is available for summer events and acknowledged short notice to affected businesses and residents.
Staff said they will continue outreach to impacted businesses and residents and will monitor complaints and logistical issues during mobilization.