Taxiway Alpha paused for winter; long-term parking bid to open with construction expected in May
Summary
Airport staff told commissioners Taxiway Alpha is in a winter pause with a tentative restart at the end of March; the long-term parking expansion bid opens soon with construction expected mid-to-late May. The manager also noted plans to buy a new fire truck and convert Building 5.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Robert Gill, Airport Manager, updated the board on multiple capital projects on March 10, 2025. He said Taxiway Alpha is in a winter pause with a tentative restart expected at the end of the month and that the long-term parking expansion bid is opening soon with construction expected to start in mid-to-late May.
Gill also told commissioners the airport plans to purchase a new fire truck and convert Building 5 to meet operational needs. No contract awards or formal procurement actions were recorded at the meeting; staff reported timelines and bid openings as part of regular project updates.
Pro Tem Chair Nick Siddle adjourned the meeting at 9:40 a.m.