Businesses flagged weeks-long closures as chief concern for Fairfield roundabout construction
Summary
City staff said typical roundabout construction can require 11–12 weeks of full road closure in all directions; staff told Mayor Steve Miller they are exploring staging the work to reduce the lengthy full-closure period, possibly to about 4–6 weeks.
Get email alerts on the Construction Timing topic
No spam. Unsubscribe anytime.
Mayor Steve Miller asked about the effect of construction on people who use River Road daily. A city staff member said contractors and concrete companies had expressed concern about long closures and described typical staging for roundabout projects. "Typically, when you build a roundabout, you'll close the road for 11 to 12 weeks and you have to close it in all 4 directions," the staff member said.
City staff said they are studying alternatives to a single extended closure, including closing side streets first and then the center of the intersection for a much shorter period. The staff member said the city hopes to reduce full-closure time to "4 or 6 weeks, or even less" once planning advances, but that exact timing is not yet known.