Town Office project tracking slightly over budget; Selectboard approves pay request No. 8
Summary
Selectboard heard a construction update: the Town Office project is about 50% complete, tracking 2–3% over budget with an anticipated August 2025 completion, and approved Pay Request No. 8.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Town Manager Rob Gaiotti reported that interior work at the Town Office is progressing and that the project is more than 50% complete. Additional tree clearing took place behind the building this week.
Gaiotti said the project is currently tracking roughly 2–3% over the budget; he and the board discussed options including use of remaining ARPA funds to cover any shortfall. The board approved Pay Request No. 8 by motion, recorded as passing 4-0.
Project managers expect to target an August 2025 completion; Naylor & Breen expressed hope of recovering schedule time during the spring.