Edgewood reconstruction to start July 13 with $1.1M grant and $2.2M loan

Richmond Heights City Council · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Engineer Justin Haselton said construction on Edgewood Road Reconstruction will begin July 13 and finish in October; the project is funded by a $1.1 million grant and a $2.2 million no-interest loan.

The Edgewood Road Reconstruction Project is scheduled to begin July 13 and be completed in October, City Engineer Justin Haselton told council on July 1. Haselton said the work was funded with a $1.1 million grant and a $2.2 million no-interest loan.

Finance Director Travian Atkins also reported the city had been awarded a $250,000 county grant toward the 2027-28 road program, which will support future pavement work. Council did not discuss changes to the Edgewood schedule or the scope of work at the meeting.