Board approves $14,175.96 change order to add ADA features at Tra Sportsplex signal

Hammond Capital Improvement Board · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Funding allocation #326 approves change order No. 2 with Milestone Contractors for $14,175.96 to add detectable warning surfaces, extend pedestrian push-buttons, and adjust curb ramps to meet NDOT/ADA requirements at the Tra Sportsplex traffic signal.

The Chair introduced funding allocation #326 as change order No. 2 with Milestone Contractors in the amount of $14,175.96 to add detectable warning surfaces and make curb-ramp and pedestrian push-button adjustments at the Tra Sportsplex signal. The Chair explained NDOT determined the installation should be treated as a traffic signal rather than a driveway, so ADA-compliant curb ramps and tactile warning strips and relocated push-buttons were required; these items were not included in the original design and thus triggered the change order. The motion to approve the change order passed by roll call.

The Chair characterized the additional work as required to meet ADA and NDOT standards rather than as design or contractor error. The board did not add further conditions to the change order during the meeting.