Suffolk reports mid‑phase progress on Lowell high‑school renovation, targets spring 2027 completion

Lowell School Building Committee · July 31, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A Suffolk representative told the Lowell School Building Committee that phase 4 construction is just under halfway complete, with basement slab work largely finished and substantial completion targeted for spring 2027. Benchmarks and walk‑throughs were set in August to confirm punch‑list and cleaning before students return.

Suffolk representatives told the Lowell School Building Committee on June 30 that work on the high‑school renovation is in phase 4 and ‘‘a little less than halfway there,’’ with the project on its eighth month and a scheduled substantial completion in spring 2027.

The presenter described visible progress in the basement — ‘‘that slab, call it 95%’’ for the 1920s portion — and said overhead MEP work, window installation and masonry demolition to enlarge classrooms in Coburn Hall have advanced. Photos compared last month’s trenching and excavation to current framing and drywall work on upper floors, and staging was visible in the future double‑height media center.

Committee members asked about remaining schedule and budget risks. Suffolk said major structural and demolition concerns are behind the project and that the remaining work is mostly finishes and more predictable, though smaller corrective items and hardware lead times remain. The contractor and staff established August 17 and August 24 benchmark walk‑throughs to confirm punch‑list completion and handoff before students return for the fall term.