425th Ave project update: bridge complete, paving expected mid-July; Board approves TIF Draw #4

Kingsbury County Board of County Commissioners · June 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Civil Design Inc. reported the 425th Ave bridge structure is complete and paving is expected around July 15, 2026; the Board approved Draw #4 on the Tax Incremental Revenue Bond, Series 2026, for $30,902.50.

Andrew Kangas of Civil Design Inc. told the Kingsbury County Board on June 18 that work on the 425th Ave project is progressing well: the bridge structure is complete and paving is expected to begin around July 15, 2026.

Auditor Echo Steffensen presented Draw #4 for the Tax Incremental Revenue Bond, Series 2026, for the 425th Ave project in the amount of $30,902.50; the Board approved the draw by motion (Lundquist/Spilde) with all present voting aye. The draw clears the listed invoice from Civil Design Inc. and funds continued project work.