Council approves $80,645 construction bond for Stony Creek Phase 2

Not specified in transcript · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials approved a construction bond of $80,645 for Stony Creek Acres Phase 2, reflecting a 20% maintenance guarantee ($6,095) and sidewalk costs calculated at $21 per linear foot with a 25% contingency; the motion passed unanimously.

The council voted to set the construction bond for Stony Creek Acres Phase 2 at $80,645 after staff presented the calculation, which includes a 20% maintenance guarantee amounting to $6,095.

Staff explained the calculation assumptions: the final course of blacktop was installed and thus a 20% maintenance guarantee was assessed; sidewalks were estimated at $21 per linear foot with a 25% contingency included in the sidewalk line item. The figures in the staff presentation applied to the 33 lots in this phase and produced the $80,645 total bond figure.

A commissioner moved to approve the bond amount and the motion was seconded. The roll call recorded aye votes from members named in the transcript — Gardner, Johnson, Richards, Lakes, Harkleroad, Embry and Ibert — and the presiding officer announced the motion passed.

The bond approval clears a financial requirement tied to final construction inspections and maintenance guarantees; staff did not record any amendments or conditions to the bond in the transcript.