Council approves correction and accepts 2024 street improvements as complete

Soap Lake City Council · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Soap Lake City Council approved Progress Estimate #5 for the Rudnick & Sons 2024 Street Improvements (including a $8,147.00 correction) and accepted the project as complete contingent on receipt of the final contract voucher.

The Soap Lake City Council voted Sept. 3 to approve Progress Estimate #5 for the Rudnick & Sons 2024 Street Improvements and later accepted the project as complete.

Councilmember Gorman moved to approve Progress Estimate #5 "with a correction to line 33 as $8,147.00," a motion seconded by Councilmember Carlson and approved unanimously. Council then moved (M/Gorman, S/Bryson) to accept the 2024 Street Improvements as complete with the contingency that the final contract voucher be received from the contractor; that motion also carried unanimously.

The actions close the city's contractual review for the multi-street pavement project pending the contractor's final voucher. Council did not record any separate amendments to scope or additional funding during the acceptance vote.