Council weighs phased approach for 7375 South/925 East street, water and storm‑drain work
Summary
City staff recommended delaying full construction of the multi‑element 7375 South/925 East project because of cost and funding limits; council members directed a temporary improvement to the gravel pedestrian path to address immediate safety concerns.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
City Manager David Larson reviewed the 7375 South 925 East Project, describing it as three distinct elements—streets, water and storm drain—and said the work is broken out by individual funds. "The three elements of the project are streets, water, and storm drain," Larson said, explaining the need to widen the road and add sidewalks because Lester Drive will connect to 7375 South.
City Engineer Brandon Jones told the council that costs rose because the work effectively combines three major projects and that "there is no current storm water connection in this area." Council members and the mayor emphasized pedestrian safety near South Weber Elementary School as a priority. Councilman Halverson noted the Public Works Department’s temporary gravel path and suggested improving it; Councilman Winsor said it made sense to do all work at once but staff are not recommending the full project now due to funding constraints. The council gave direction to improve the gravel trail as a temporary fix while deferring full construction pending funding, and Finance Director Brett Baltazar will continue to assess budget options.