Designers explain one‑story preference and cost tradeoffs for Boxborough station

Town of Boxborough Fire Station Building Committee · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects said a one‑story layout was chosen after preliminary cost work and geotechnical review showed excavation/ledge removal could offset savings from a two‑story scheme; the team said the one‑story plan improves direct access to apparatus.

Designers said they studied a two‑story scheme but preliminary pricing and site conditions led the committee to favor a one‑story plan. The team said some perimeter areas on the site contain shallower bedrock and that additional excavation and selective ledge removal for a two‑story footprint could increase costs.

A resident who worked in construction challenged that claim; Rebecca Hoy (former project manager) said she had not seen architects state that an expanded footprint could be more expensive than a second floor. Chris Logan replied that on this specific site, geotechnical data suggest extra site work might offset typical savings of building up.

The design team estimated a small preliminary cost delta (1–2% in early estimates) between the schemes but emphasized those figures are preliminary and that detailed cost estimating is ongoing as the project moves into later design phases.