Oklo says first commercial plant at INL could begin producing power by 2027–28

University of Utah, Price College of Engineering panel on advanced nuclear · June 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Oklo CEO Jake DeWitt told a University of Utah panel the company has a site-use permit with DOE, is doing ground characterization and aims to break ground soon on a commercial demonstration plant at Idaho National Lab, targeting late 2027–28 for first power.

Jake DeWitt, chief executive of Oklo, described a path to a commercial demonstration at Idaho National Laboratory: a site-use permit with DOE, INL-supplied fuel and ongoing ground characterization and drilling. "We're building our 1st plant up in Idaho. It's a full commercial plant. It's cited on the lab," DeWitt said, and added that the project is intended to be a pathfinder for private deployment backed by offtakers and investors.

DeWitt framed data centers and other large, predictable electricity customers as critical early customers that can support higher first-of-a-kind prices and help drive down costs for subsequent plants. He said Oklo sized its technology to match typical data-hall loads (about 60–75 megawatts) and that having well-capitalized customers changes the financing dynamics for early builds. The panel offered no regulatory dates beyond company targets.