Council awards 40th Street waterline contract to Brager & Sons
Summary
City staff recommended and council approved a contract with Brager & Sons for the 40th Street waterline replacement; staff noted the pipe dates back to the 1930s and that competitive bids came in well under the engineer’s estimate.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
The South Ogden City Council voted to award a contract to Brager & Sons for the 40th Street waterline project (Resolution 25-06). Public Works and Parks Director John Anderson recommended the award after an A/B bid process and said the project will replace aging line that has leaked in prior summers.
“We were actually able to get 7 bids, which is phenomenal for us,” Anderson said, describing a competitive bidding outcome. He told council the pipe at the project end is old — observed fragments suggest it could date to the late 1930s — and that the work will require a planned shutdown and a roughly 90-day construction window.
Anderson explained the engineer’s estimate and supplies cost, and council asked for clarifications about total cost; staff confirmed anticipated costs will be closer to $1,000,000 once supplies and allowances are included, but the winning bid came in substantially under some estimates. Council moved, seconded and approved the resolution in a roll-call vote.
Staff said they will coordinate scheduling, public notification for shutdowns and follow-up outreach to adjacent property owners before construction begins.