Florence approves $78,928.62 contract increase for Eagle Post Road sanitary sewer project
Summary
The board approved MCWI Contract Change Order #4, increasing the Hwy. 49 Eagle Post Road Sanitary Sewer Additions — Phase II contract by $78,928.62; the motion carried, and Alderman Mason Herrin did not participate in the vote having left earlier.
Get email alerts on the Sanitary Sewer Contracts topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker recommended approval of MCWI #255-2-CW-5.5 — Contract Change Order #4 — which increases the contract for the Hwy. 49 Eagle Post Road Sanitary Sewer Additions — Phase II by $78,928.62. Alderman John Banks moved the change order and Alderman Kyle Martin seconded; the motion carried by a unanimous vote among members voting.
The minutes note that Alderman Mason Herrin left the meeting prior to the vote and was later invited to return, with a record statement that he "had not participated nor deliberated in no wise for the city." The board also authorized the mayor to sign close-out documents for the related STP–Eagle Post Road overlay project on City Engineer Tim Parker's recommendation earlier in the meeting.