Mountrail County approves $23.677 million CR4 rebuild, agrees 50/50 utility relocation with MWEC

Mountrail County Board of Commissioners · May 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county voted May 5 to reconstruct County Road 4 as a single 11-mile project in 2029 (Alternative 1A) with an estimated roadway cost of $23,677,000 and estimated utility relocation cost of $3,705,000, to be split 50/50 with Mountrail Williams Electric Cooperative.

Mountrail County commissioners voted May 5 to move forward with a full reconstruction of County Road 4 (74th St NW) as one project in 2029, approving Alternative 1A, which includes a west-end alignment shift. The motion, moved by Commissioner John DeGroot and seconded by Commissioner Jason Rice, passed unanimously.

Road & Bridge Engineer Jana Hennessy and representatives from HDR Engineering presented four design options and associated cost estimates: a single-project build ($22,295,000), two-part and three-part builds (roughly $23.3M–$23.9M), and alignment/realignment options raising costs to about $23.677 million. The approved Alternative 1A carries an estimated roadway cost of $23,677,000 and an estimated utility relocation cost of $3,705,000; the Board approved splitting the utility relocation costs 50/50 with Mountrail Williams Electric Cooperative (MWEC). A cost-share agreement will be presented to the Board at a future meeting for formal approval of the detailed terms.

The Board’s action commits the county to a multi-million-dollar capital project that will proceed next into formal design, right-of-way and utility coordination phases. County staff emphasized the need for subsequent agreements and inspections tied to utility relocations and rights-of-way prior to construction.