Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater topic

No spam. Unsubscribe anytime.

Henderson board rejects East Lagoon dredging bids after sludge estimate jumps

Board of Mayor and Aldermen of the City of Henderson · March 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utility Director Darryl Green told the board sludge estimates rose from 50 to about 800 dry tons — raising a pro forma cost to roughly $6 million — prompting the board to reject bids and require revised specifications for rebidding in April.

The Board of Mayor and Aldermen voted to reject bids for dredging the East Lagoon after Utility Director Darryl Green told the board the sludge estimate had been recalculated from an initial figure of 50 dry tons to about 800 dry tons, which he said would have pushed a cost estimate to roughly $6 million.

Green said he will re-advertise the project with corrected dry-ton estimates and return to the board with updated bids in April. Alderman Keith Smith moved to reject the bids and Alderman Michael Phelps seconded; the motion carried. The board discussed the procurement implications of the larger volume and the need to adjust contract specifications before reissuing the solicitation.