Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sewer Infrastructure topic

No spam. Unsubscribe anytime.

Henderson approves $671,201 sewer project to eliminate flood‑prone Hwy 45 pump station

Board of Mayor and Aldermen of the City of Henderson, Tennessee · October 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council accepted a $671,201.40 bid to rebuild pump stations and install a 12‑inch gravity sewer line beneath US Hwy 45 to reduce backups in a low‑lying area and remove the need for one pump station.

Utility Director Darryl Green described persistent problems at the pumping station on US Hwy 45, which sits in a low‑lying flood area and has caused backups to some residences in rainy periods. The board approved a plan to bore under the highway and install a 12‑inch gravity‑flow line across the Henderson Industrial Park to the outfall next to the railroad track, eliminating the pump station.

Only one bid was received for the work; the board accepted R. Jones Underground’s bid of $671,201.40 following a motion by Alderman Mark A. Barber and a second by Alderman Buel Maness. The minutes record that replacing pump stations is expensive, and the gravity-line approach is intended to reduce future maintenance and backup complaints.