Cass County awards striping and gravel contracts for 2026 season; bids well under engineers’ estimates
Summary
The board awarded the 2026 maintenance striping contract to Sir Lines‑A‑Lot for $339,647.64 and the 2026 gravel surfacing contract to DLL Excavating for $238,771.80; both bids came in substantially below engineer estimates.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
County Engineer Darrick Anderson presented bids and recommended awards for two roadwork contracts at the April 7 meeting. For the 2026 Maintenance Striping project (C.M. 2026‑02) covering roughly 387.5 miles of paved roadway (12.4 miles epoxy, 375.1 miles latex), Sir Lines‑A‑Lot submitted the low bid at $339,647.64 against an engineer’s estimate of $424,507.07. Anderson said the county will use higher‑durability epoxy on routes with more than 1,000 vehicles per day and latex elsewhere; funding comes from maintenance levy funds.
For the 2026 Gravel Surfacing contract (C.M. 2026‑01) involving hauling gravel to about 36 miles of road, DLL Excavating’s low bid was $238,771.80 — roughly 32% under the engineer’s estimate. Anderson noted material costs approx. $11.18/ton using crushed material from 2025 pits and that an intern will be stationed at the pit to monitor loader tickets. The board unanimously awarded both contracts.