Highway director gives timeline for Bridge 95 and updates on Bridges 154 and 211
Summary
Deputy Highway Director Robyn Hughes reported Bridge 95 repairs starting July 10 with an estimated 30‑day timeline and said I‑beams for Bridges 154 and 211 are expected by Aug. 4.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
During the July 6 meeting Deputy Highway Director Robyn Hughes updated commissioners on several bridge and pavement projects.
Hughes said work on Bridge 95 is scheduled to begin July 10 with an estimated 30‑day repair window. She also reported that components for Bridges 154 and 211 have been ordered and that the county expects delivery of I‑beams by Aug. 4. Hughes provided a general update on hot‑mix paving and chip seal work underway or planned for county roads.
Commissioners received the report; no separate motions were required beyond the Huffman bridge action recorded during the highway report.