Summary
Bids submitted March 31 for two renovation projects at 631 E. Robinson ranged from $60,000 to $245,450 across Project A and Project B; commissioners accepted bids and directed Purchasing to tabulate and qualify proposals before award.
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
The board opened bids for BID #COM-2141 covering two renovation projects at 631 E. Robinson (the old DHS building). Project A (TF Office Space) bids ranged from $115,000 to $245,450; Project B (OSU Extension Office) bids ranged from $60,000 to $127,750. Alternates and exclusions were noted on several proposals; one alternate offered a $25,000 reduction if both projects were awarded to the same contractor.
Commissioners accepted the bids, postponed award and instructed Purchasing to tabulate and qualify each bidder before making a recommendation. The board recorded unanimous support for postponement; a report will be prepared for a future meeting prior to any contract award.