Oak Ridge Drive awarded to DDM Construction; transportation bond projects advance

Parker County Commissioners Court · December 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The court awarded Oak Ridge Drive construction to DDM Construction for $11,869,805.04, approved phase budget reallocations and heard a monthly transportation bond update including a TxDOT permit for the US-377/Kelly Road signal.

Parker County Commissioners Court approved an award for Oak Ridge Drive and moved several bond-era projects forward in its Dec. 8 meeting.

Dustin, presenting the bid results, said the county received four bids and recommended awarding the base bid plus alternate B and alternate D to DDM Construction. “So we're asking to award this contract to DDM Construction in the amount of $11,869,805.04,” the presenter said. Commissioners approved the award by unanimous vote.

Staff also outlined the program budget: Oak Ridge total project costs across phase 1 and phase 2 are nearly $15,000,000, with a phase 1 budget of roughly $11,000,000. The court approved proposed budget reallocations to fund phase 1 work and related county-conducted construction tasks.

In a broader update, Morgan McElwain of Friese Nichols summarized monthly coordination with NetCOG, TxDOT and municipalities. She told the court TxDOT agreed to a permit for the U.S. 377/Kelly Road signal — a development the county described as removing the need for an access-flag agreement and speeding delivery for that intersection.

The court also approved routine bond-related items including moving a maintenance-bond call for Ellis Creek improvement projects and scheduling bid openings for other roadways.