Oakland's $4.2M in impact fees shrink; $34M five-year CIP dependent on Amendment 3, grants
Summary
Staff reported $4.2M in impact fees with $2.4M budgeted for projects and $1.7M in reserve; a five-year capital improvement program of about $34M is largely grant-dependent and contingent on the outcome of Amendment 3.
Get email alerts on the Capital Improvements topic
No spam. Unsubscribe anytime.
Town staff told commissioners the impact fee fund balance is about $4.2 million, with $2.4 million budgeted for immediate projects and approximately $1.7 million reserved for future needs. Gabby said the impact-fee total declined by about $900,000 over the prior year because multiple projects drew from that fund.
She reviewed changes to project budgets: the Northwest Loop water-plant design allocation increased by $150,000 (reducing a larger $500,000 planning line), parks pavilion amounts rose with inflation but were constrained by the town's agreement with a nature preserve, and hydrant upgrades and water-line work prompted an increase in fire-protection impact-fee allocations. Gabby emphasized the town has five-year capital improvements totaling about $34 million but described the CIP as contingent on Amendment 3 and the success of grant applications.
Mike Parker noted roughly $7.5 million in water grants are listed, including $4 million for alternative water construction and $3.5 million for septic-to-sewer work; Gabby said grant funds often cover construction but design costs typically come from town funds.