Courthouse renovation nears completion on main roof; windows, bell tower and water-damage work continue

Blackford County Board of Commissioners · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager Derek Hagan reported the main courthouse roof is finished, scaffolding for the bell tower is being erected, windows are being installed and masonry work continues. Facilities manager Meagan Westfall said HVAC is performing well and that Annex water-damage quotes remain pending.

Derek Hagan, courthouse renovation project manager, told the commissioners that the main roof work is finished and scaffolding to access the bell tower is being installed. He said windows are still being installed and masonry crews remain on site.

Meagan Westfall, courthouse facilities manager, reported that the courthouse HVAC has been performing well. She said another quote is expected for first-floor Annex water-damage repairs and that water-fountain filters are on back order.