Courthouse roof finished; arched windows delayed, insulation and third-floor work continuing
Summary
Project manager Derek Hagen reported the main roof on the Blackford County Courthouse is finished, attic insulation spraying is expected to finish by the end of the month, third-floor window replacements are underway and arched windows are delayed until December.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Derek Hagen, the courthouse renovation project manager, told the commissioners on Oct. 7 that the main roof is finished and scaffolding is being removed. He said spraying of attic insulation should be completed by the end of October and that third-floor windows are being replaced.
Hagen noted that the arched windows are delayed and are expected by December. The minutes record these timeline items but do not include cost updates or a revised completion date for the entire project.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.