Clock tower scaffolding rises as courthouse roof work nears completion

Blackford County Board of Commissioners · August 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager Derek Hagan reported scaffolding is being erected to the clock tower, masons are working on the east side, and the roof — except the clock tower — is expected to be completed by the end of the month; window work is underway.

Derek Hagan, the courthouse renovation project manager, told commissioners on Aug. 5 that scaffolding is being erected to the clock tower and masons are working on the east side of the courthouse. He said, except for the clock tower, the roof should be completed by the end of the month and Shorts Glass is installing and trimming windows.

The report focused on construction progress; Hagan did not provide a final completion date for the clock tower work. Commissioners accepted the update and did not take additional action at the meeting.

Staff and contractors are coordinating exterior masonry and roofing tasks; the board will review further status reports as work progresses.