Midway council backs Town Square master plan; prioritizes recreation building and ice-rink work to protect grants
Summary
Council members endorsed a comprehensive Town Square master plan for 150 West Main Street but agreed immediate work must focus on designing a qualifying recreation building and critical ice-rink upgrades to preserve grant funding and allow phased future improvements.
Get email alerts on the Town Square Master Plan topic
No spam. Unsubscribe anytime.
The Midway City Council on July 21 reviewed a proposed Town Square Master Plan for the municipal block at 150 West Main Street and agreed the plan should guide long-term improvements while prioritizing a recreation building and ice-rink upgrades needed to retain current grant funding.
Staff presented design concepts that include north-south and east-west promenades, relocation of central parking to create a larger green gathering area, stronger connections to Main Street and Centennial Park, additional seating and shade, and facilities to support year-round community events. Council members said the master plan must remain a flexible, phased blueprint rather than a single large-dollar project.
Council discussion focused on which elements to tackle first. Members repeatedly emphasized that constructing a qualifying recreation building and completing ice-rink and chiller-system improvements are time-sensitive because grant awards require an eligible project. Nancy O'Toole highlighted additional grant opportunities, including a new rural UDOT program that could fund sidewalks, trails, parking, and other public improvements without a local match.
Concerns raised included the tight timeframes for qualifying projects under grant deadlines, the overall cost of executing the full master plan, and trade-offs from reducing parking in Town Square while preserving access for downtown businesses, Swiss Days, and city facilities. Several members questioned the wisdom of a new water feature given drought conditions and ongoing maintenance costs.
Council conclusions directed staff to revise the master plan with a realistic phasing strategy, prepare updated building concepts that meet grant qualifications, and return the revised plan for further consideration. Staff were expressly told to prioritize concepts that enable year-round recreation and to obtain state or grant-agency approvals prior to committing funds or construction.