Alpha Delta Phi presents infrastructure renewal and accessibility plan for historic Cornell House

Ithaca City Planning and Development Board · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Alpha Delta Phi presented a consolidated resubmittal addressing PRC comments: a compact electrical/mechanical building on the north side, an ADA‑compliant ramp to the lower level, site grading, and modest landscape upgrades. The board opened and closed a public hearing with no public speakers and signaled general support for the resubmission.

Alpha Delta Phi's team described a package of civil and architectural drawings that respond to prior PRC comments and provide a plan for long‑term mechanical and accessibility upgrades to the 1930 fraternity building.

Greg Williamson explained the rationale for a north‑side mechanical/electrical addition: many of the building's systems have reached the end of their useful life and the team needs a compact, unoccupied space to house upgraded switchgear, mechanical tanks and an automatic transfer switch to support electrified heating and freeze protection. "The house has reached the end of useful life in many of its building systems. It was built in 1930," Gregory said when summarizing the need for an infrastructure renewal.

The resubmission includes an ADA ramp to the lower level, stone veneer gravity terraces to manage grade and a proposed small patio on the protected south side. The board opened a public hearing (no public comments) and members said the packet addressed PRC recommendations; the board signaled that, with the planned clarifications, the submission is in good shape for the next PRC and planning board reviews.

Next steps: designers will provide final planting details and confirm drainage tie‑ins; the board asked for any remaining technical clarifications prior to formal approvals.